- Environmental impact assessment study
- Marine investigations (bathymetry, wave, tide, current, etc.) and geotechnical investigations
- Design of the infrastructure works: jetties, rock armors, coastal protection
- Stability of the works, project wave
- Checking and control in specialized centers
- Structure design of the quays and decks
- Layout of the superstructures
- Technical Specifications
- Supervision of works
Project | Supervision of Construction Works of the Commercial Port in Saida (Phase 2) - Lebanon |
---|---|
Project Duration | 2018 - Present |
Client | Lebanese Government |
Project Description |
|
Project | Supervision of the Rehabilitation of Saida Fishermen Port - Lebanon |
---|---|
Project Duration | 2018-Present |
Client | Lebanese Government c |
Project Description |
|
Project | Supervision of Saida Port Center Building - cLebanon |
---|---|
Project Duration | 2018-Present |
Client | Lebanese Government c |
Project Description |
|
Project | Feasibility Study for the Second Phase of Saida Commercial Port - Lebanon |
---|---|
Project Duration | Saida Commercial Port |
Client | Lebanese Government |
Project Description |
|
Project | Design of Rehabilitation of Works for Marine Structure at Jieh Power Plant - Lebanon |
---|---|
Project Duration | 2016-2017 |
Client | Lebanese Government |
Project Description |
|
Project | Supervision of the Rehabilitation of Saida Fish Market - Lebanon |
---|---|
Project Duration | 2016-2017 |
Client | Lebanese Government |
Project Description |
|
Project | Supervision of Aadloun Port - Phase 1 & 2 - Lebanon |
---|---|
Project Duration | 2015-2018 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Project | Supervision of Nahr El Kalb - Holiday beach - Sand Dredging - Lebanon |
---|---|
Project Duration | 2015-2018 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Project | Design of protection of Marine School Batroun - Lebanon |
---|---|
Project Duration | 2014-2015 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|
Project | Design of Aadloun Port Lebanon |
---|---|
Project Duration | 2012-2013 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|
Project | Supervision of Nahr El Kalb - Holiday beach - Sand Dredging Lebanon |
---|---|
Project Duration | 2011-2013 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|
Photos |
Project | Design of Dbayeh Port Lebanon |
---|---|
Project Duration | 2011-2012 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|
Project | Design of Saida Commercial Port Lebanon |
---|---|
Project Duration | 2010-2011 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|
Project | Design and Supervision of Aquaibeh Port Lebanon |
---|---|
Project Duration | 2010-2012 |
Client | Ministry of Public Works and Transport |
Project Description |
|
Services Description |
|